Kalan Deme So school in Dougourakoro: low classroom building with coloured bamboo cladding, between two shea trees, at the foot of a rocky hill.
1 / 4

©Chiwarà Project — Dougourakoro, Mali

Country · location
Mali · Dougourakoro
Type
Education infrastructure
Surface area
710 m², 3 blocks of 3 classrooms
Completion
March 2023
Technique
Locally produced compressed earth blocks, ventilated double-layer walls, vaults and ventilated roof
Our role
Designer and works supervisor

Status

Completed

Mali · Dougourakoro · Education · Design and supervision

Kalan Deme So school complex

The spread of concrete and imported materials is causing an irreparable loss of Malian know-how, traditional techniques and local materials. It increases communities’ dependence on imports and holds back both their development and their resilience.

The project combines passive cooling techniques with compressed earth blocks made on site to give pupils a pleasant school environment, despite extreme temperatures and the absence of electricity. Three blocks of three classrooms were designed and built, with ventilated double-layer walls, vaults and a ventilated roof.

Our scope of work

  • Design of the complex and its bioclimatic construction strategy
  • Technical solutions in compressed earth blocks and ventilated envelopes
  • Supervision of the construction of the three blocks
  • Monitoring of technical quality and site execution
  • Coordination with the contracting authority and the local contractor

Results

What was delivered

3school blocks

of three classrooms each

710m²

of education infrastructure completed

9classrooms

in compressed earth blocks produced on site

2023

completed in March, with double-layer walls and a passive roof strategy

  • Three school blocks of three classrooms each
  • 710 m² of education infrastructure delivered
  • Double-layer compressed earth block walls and passive roof

Source: signed performance certificate.

Partners

Client
  • Ka Mali Deme, Helft Mali e.V.
Donor
  • Fundraising
Contractors
  • Barazi Entreprise
  • Entreprise Amatigue Dara
Partners
  • Agrebattechnical partner
  • BICE Conseilstechnical partner
Evidence

Signed performance certificate.

Techniques used

Compressed earth blocks, ventilated double-layer walls

Blocks produced locally from the site’s soil; ventilated double-layer walls for thermal mass and comfort.

Vaults and ventilated roof

Passive roof strategy: a ventilated air gap above the vaults, and a covered gallery acting as a sunshade.

Passive design

Orientation, shading and cross ventilation of the classrooms, to improve comfort and reduce environmental impact.

Let’s work together

Planning a construction project in Mali?

Country, type of assignment and stage of progress: a few lines are enough for a useful first reply.

Let’s talk about your project
Contact us

info@chiwaraproject.com